Should a small importer hold more safety stock during route disruption?

How would you add a buffer without tying up cash in products that already sell slowly?

8 replies

  1. I'd start with the items that have both uneven replenishment and a painful stockout. Applying the same extra weeks to every SKU usually creates a lot of sleepy inventory. A simple first pass is to put products into a few groups: essential fast movers, replaceable items and slow or seasonal stock. You can then discuss a different buffer for each group instead of arguing over one company-wide number that fits none of them particularly well.
  2. Separate supplier production variation from transport variation. Otherwise you may blame the vessel for a problem that really starts before the goods are packed.
  3. Use recent actual receipt dates for the lane, then look at the slower cases as well as the average. An average can hide the delays you are trying to cover.
  4. Cash availability should be part of the discussion from the start. A buffer that makes the next supplier payment difficult isn't much of a safety net.
  5. For short shelf-life stock, I'd lean toward smaller, more frequent replenishment if transport options allow it. Extra inventory can become a write-off very quickly.
  6. A backup supplier only helps if the product is already approved. I'd count qualification time in the plan instead of treating an untested quote as immediate capacity.
  7. Pick a review date when you add the buffer. Temporary disruption stock has a habit of becoming permanent because nobody owns the decision to reduce it.
  8. Don't forget open purchase orders already in transit. Before buying more, lay out what arrives when and which customer demand is already covered.